Bitget App
Trade smarter
Buy cryptoMarketsTradeFuturesStocksEarnInstitutionAI & More
B2Gold commissions mobile crusher after April fire at Goose Mine disrupts fixed plant

B2Gold commissions mobile crusher after April fire at Goose Mine disrupts fixed plant

BitgetBitget2026/09/28 11:03
  • B2Gold commissioned a new mobile crushing plant at Goose Mine in August, stabilizing ore crushing capacity following an April fire.
  • Mobile crushing has averaged more than 3,000 tonnes per day since mid-August, matching plan.
  • Fixed-plant repairs tied to fire damage are scheduled to finish in mid-October, targeting sustained throughput of 3,200 tonnes per day.
  • The company kept 2026 Goose output guidance unchanged at 170,000 to 200,000 ounces of gold.
  • Capital spending totaled about USD 16 million for the mobile plant, with USD 11 million for Phase 1 fixed-crusher upgrades.


Disclaimer: This news brief was created by Public Technologies (PUBT) using generative artificial intelligence. While PUBT strives to provide accurate and timely information, this AI-generated content is for informational purposes only and should not be interpreted as financial, investment, or legal advice. B2Gold Corp. published the original content used to generate this news brief via GlobeNewswire (Ref. ID: 202609280700PRIMZONEFULLFEED9834774) on September 28, 2026, and is solely responsible for the information contained therein.

0
0

Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.

Understand the market, then trade.
Bitget offers one-stop trading for cryptocurrencies, stocks, and gold.
Trade now!