KGHM completes Głogów II copper smelter overhaul early, restores production line
Bitget2026/10/02 11:47- KGHM completed a major maintenance outage at the Głogów II copper smelter ahead of schedule, restoring full operations.
- The outage halted the flash furnace line on June 28, then shut the electric furnace the next day.
- Work covered the full production line, with spending described as several hundred million zlotys.
- Commissioning restarted concentrate smelting on Sept. 16, 2026; electric furnace work finished on Sept. 30, ending the outage.
- The overhaul extends the interval between major maintenance outages to five years from four, supporting higher reliability and lower smelting costs.
Disclaimer: The content of this article solely reflects the author's opinion and does not represent the platform in any capacity. This article is not intended to serve as a reference for making investment decisions.
You may also like

US Stock Movement | Qualcomm (QCOM.US) rises more than 4% in pre-market trading after reaching a multi-year patent licensing agreement with Huawei
Huawei and Qualcomm (QCOM.US) announced on Monday that they have reached a comprehensive multi-year patent licensing agreement.
Dow Jones futures slip as Middle East tensions offset Fed rate cut hopes
DBS CIO: Nvidia (NVDA.US) has a forecast P/E ratio of only 17, AI tech stocks are far from bubble territory
The price-to-earnings ratio of NVIDIA (NVDA.US) and its projected 70% earnings growth next year indicate that AI-driven tech stocks are far from entering bubble territory.